SHORANUR-KUTTIPURAM-CALICUT

                                                          (DOUBLING)                                 (Rs. in crores)

Length

in km

Year of sanction

 

Anticipated cost

 

ROR

Expenditure

upto last financial year

Outlay for

2005-06

86

1994-95

188.13

13.43%

135.27

15.00

Remarks

 

Estimate sanctioned by Railway Board for Rs. 112.92 Crores for Kuttipuram - Calicut section and Shoranur-Kuttipuram material modification detailed estimate for Rs.64.42 Crores also sanctioned by Railway Board.  Reach works including minor bridge work are in various stages of progress between Shoranur and Kuttipuram.  Old track is decommissioned on Calicut - Kallayi and Kadalundi - Parapanangadi sections for yard remodelling / SRSF works. Doubling completed between Calicut - Kuttipuram.  CRS/SBC has inspected this section on 19/07 & 20/07/2005 between Tanur and Tirunavaya (16.50 km) and the section is commissioned for traffic on 20/07/2005. Tirunavaya - Kuttipuram section NI work will be introduced during Aug. 05 for commissioning of the doubling line.