MAVELIKKARA-KAYANKULAM(DOUBLING) (Rs. in crores) |
|||||
Lengthin km |
Year of sanction |
Anticipated cost |
ROR |
Expenditureupto last financial year |
Outlay for 2005-06 |
7.89 |
2003-04 |
21.84 |
5.108% |
6.76 |
5.00 |
|
|
|||||
|
Remarks
Requirement of land for about 6.80Ha (Revised) has been given to state Govt. 4(1) Notification has been issued by state Govt. 5.60Ha handed over so far. Estimate is sanctioned by GM/MAS for Rs.26.81 crores on 26/07/2005. Work in progress for one major bridge and one RUB. Tenders for Earthwork and minor bridges under finalisation. Agency fixed for ballast collections.
|
|||||