CALICUT-MANGALORE(DOUBLING) (Rs. in crores) |
||||||
Lengthin km |
Year of sanction |
Anticipated cost |
ROR |
Expenditureupto last financial year |
Outlay for 2005-06 |
|
221 |
1995-96 |
572.51 |
13.43% |
505.92 |
10.00 |
|
|
|
|
|||||
|
Remarks
Estimate sanctioned. Work in progress. 218.30 out of 220.64 km commissioned. Thus doubling of track is completed from Calicut to Netravathi near Mangalore. Old track has been taken up for re-grading on Cannanore � Valapattinam and Kasargod � Kotikulam section.
The main bottleneck on the Netravathi-Kankanadi section (doubling is being taken to Kankanadi instead of Mangalore) is the construction of the bridge across Netravathi river. As far as Netravathi bridge (28x21.4m+2x45m) is concerned, 60% of piles, 40% of pile caps and 30% of trestle columns have been completed. As the progress of the works were too slow, termination of the agency executing the foundation work was processed. However, prior to issue of the termination notice, the agency approached the Hon'ble High Court of Madras and got a stay against risk & cost proceedings. Counter has been filed and the stay has been got vacated recently. Risk and cost tender called for bridge foundation. Earthwork and remaining bridge works are in progress from Netravathi to Kankanadi. |
|
|||||