CHEPPAD-KAYANKULAM(DOUBLING) (Rs. in crores) |
|||||
Lengthin km |
Year of sanction |
Anticipated cost |
ROR |
Expenditureupto last financial year |
Outlay for 2005-06 |
7.76 |
2003-04 |
21.48 |
-2.935% |
5.48 |
2.00 |
|
|
|||||
|
Remarks
The final location survey for the work has been completed. working plan and working section approved. Yard plans of Kayankulam and Cheppad approved. Estimate is sanctioned by GM for Rs.26.24 crores on 26/07/2005. Requirement of land for 6.50Ha(revised) has been given to the State Government. 6.20Ha (Revised) handed over so far. Tenders for Earthwork and minor bridges under finalisation. Tender for collecting ballast in yards is under finalisation.
|
|||||