ANGAMALAI � SABARIMALA(NEW LINE) (Rs. in crores) |
|||||
Lengthin km |
Year of sanction |
Anticipated cost |
ROR |
Expenditureupto last financial year |
Outlay for 2005-06 |
|
146 |
1997-98 |
550.00 |
-2.1% |
5.62 |
1.00 |
|
|
|||||
|
Remarks
Railway Board's procedural approval was obtained. Forest department is not allowing Railways to pass through Tiger Reserve Forest. So Board ha ve decided to terminate the new line at Azutha. Final location survey was completed upto Azhutha. Working plan and section approved. Part detailed estimate for four major heads for Angamali - Azhutha section for Rs.552.29 crores submitted to Railway Board. CE/CN/TVC had attended Board on 6/01/2005 and modified the estimate for Rs.517.70 crores. Further Boards query has been replied on 9/3/2005 , 22/03/05 & 20/05/05
Total land required is 516.42 Ha. Out of this, requisition is given for 470.86Ha. Still no land has been handed over to Railway. During the meeting held with Hon'ble Chief Minister of Kerala on 28/03/2005 the matter was pursued. He decided to hold separate meeting with the concerned MLAs of the area for taking their views on the matter. Meeting called by Hon'ble Minister for water Resources & Parliamentary affairs (In charge of Railway matters), Govt. of Kerala on 2/6/2005. But nothing conclusively decided. |
|||||